The Sandur Manganese & Iron Ores Limited Obtains Environmental Clearance to Boost Iron Ore Output to 9.42 Million Tonnes Per Annum
Clearance includes reduction in manganese ore capacity and approval for beneficiation plant reconfiguration within existing mining lease of 1860.10 hectares
The Sandur Manganese & Iron Ores Limited has obtained environmental clearance from the Ministry of Environment, Forest and Climate Change to increase its iron ore production capacity from 7.85 MTPA to 9.42 MTPA and reduce manganese ore capacity from 1.34 MTPA to 0.7330 MTPA. The clearance also approves reconfiguration of the beneficiation plant with no change to the 1.2 km downhill conveyor system within an 1860.10 hectare mining lease area.
The Sandur Manganese & Iron Ores Limited
Capacity Expansion
The Sandur Manganese & Iron Ores Limited has been granted environmental clearance by India's Ministry of Environment, Forest and Climate Change to increase its iron ore production capacity to 9.42 million tonnes per annum, while reducing manganese ore capacity and reconfiguring its beneficiation plant.
The company’s Mining Lease No. 2678 covering 1860.10 hectares has received clearance for an enhanced iron ore run-of-mine (RoM) capacity from 7.85 million tonnes per annum (MTPA) to 9.42 MTPA.
Simultaneously, manganese ore RoM capacity is reduced from 1.34 MTPA to 0.7330 MTPA as permitted under the new clearance.
The beneficiation plant will be reconfigured from a single 7.00 MTPA unit to two units of 3.5 MTPA each.
The approval maintains the existing 1.2 km downhill conveyor system within the mining lease area without any changes.
The company plans to seek further regulatory approvals necessary to operate at the updated production levels.
Highlights
- Environmental clearance granted by Ministry of Environment, Forest and Climate Change on 11 November 2026.
- Iron ore production capacity increased to 9.42 MTPA from 7.85 MTPA.
- Manganese ore capacity reduced to 0.7330 MTPA from 1.34 MTPA.
- Beneficiation plant reconfigured from 1 x 7.00 MTPA to 2 x 3.5 MTPA.
- Mining lease spans 1860.10 hectares with no change to 1.2 km downhill conveyor system.
Key Data Snapshot
What happened
- The Ministry of Environment, Forest and Climate Change granted environmental clearance to The Sandur Manganese & Iron Ores Limited for capacity changes in its Mining Lease No. 2678.
- Iron ore run-of-mine capacity will increase from 7.85 MTPA to 9.42 MTPA.
- Manganese ore run-of-mine capacity will reduce from 1.34 MTPA to 0.7330 MTPA.
- The beneficiation plant configuration will change from a single 7.00 MTPA unit to two 3.5 MTPA units.
- No modification to the approved 1.2 km downhill conveyor system within the mining lease area was made.
Regulatory and governance context
- The clearance was issued following the company’s application under Para 7(ii)(a) of the EIA Notification, 2006.
- Further regulatory approvals will be initiated by the company for operations at the enhanced production capacity.
- The clearance falls under the jurisdiction of the Ministry of Environment, Forest and Climate Change, Government of India.
Highlights
- Environmental clearance granted by Ministry of Environment, Forest and Climate Change on 11 November 2026.
- Iron ore production capacity increased to 9.42 MTPA from 7.85 MTPA.
- Manganese ore capacity reduced to 0.7330 MTPA from 1.34 MTPA.
- Beneficiation plant reconfigured from 1 x 7.00 MTPA to 2 x 3.5 MTPA.
- Mining lease spans 1860.10 hectares with no change to 1.2 km downhill conveyor system.
Disclosures
- EIA Notification, 2006, Para 7(ii)(a)
More News on Capacity Expansion
View allLatest corporate announcements and market updates in Capacity Expansion.
Juniper Green Energy Raises Operational Capacity to 2,952 MWp with Commissioning of 108.50 MWp Solar Component in Hybrid Project
Juniper Green Energy Limited announced that its wholly owned subsidiary Juniper Green ETA Five Private Limited has commissioned 108.50 MWp of solar capacity as part of a 75 MW wind-solar hybrid power project with Maharashtra State Electricity Distribution Company Limited on November 19, 2026.
Read Full StoryJuniper Green Energy Subsidiary Commissions 94.77 MWh Battery Energy Storage System on November 19, 2026
Juniper Green Stellar Private Limited, a wholly owned subsidiary of Juniper Green Energy Limited, has commissioned a 94.77 MWh Battery Energy Storage System on November 19, 2026. This capacity is currently deployed as a merchant capacity with flexibility to convert to a long-term Power Purchase Agreement in the future.
Read Full StoryACME Solar Holdings Commissions 155.71 MW Renewable Energy Project With Battery Storage in Rajasthan
ACME Solar Holdings Limited announced commissioning 155.71 MW of its Firm and Dispatchable Renewable Energy project in Rajasthan, comprising a 100.02 MW solar plant and a 55.69 MW battery energy storage system, on November 19, 2026, with commercial operations starting from November 21, 2026.
Read Full Story