Tata Power Renewable Energy Commissions 100.8 MW Ausa Wind Project with First-Ever Monopole EHV Line
Project to generate 308 million units annually and reduce 2.52 lakh tonnes of CO₂ emissions, expanding Tata Power Renewables' capacity to 12.1 GW
Tata Power Renewable Energy Limited has commissioned a 100.8 MW wind energy project in Ausa, Maharashtra, expected to generate 308 million units of clean electricity annually and reduce 2.52 lakh tonnes of CO₂ emissions. The project features India's first monopole extra high voltage line installation for wind power, boosting Tata Power Renewables' total renewable capacity to 12.1 GW.
The Tata Power Company Limited
Capacity Expansion
Tata Power Renewable Energy Limited has commissioned a 100.8 MW wind power project in Ausa, Maharashtra, expected to generate 308 million units of clean electricity annually and supply renewable power to Tata Power Mumbai Distribution (TPC-D).
The wind project consists of 28 Horizontal Axis Wind Turbine Generators (model SG 3.6-145).
The project will help reduce approximately 252,560 tonnes of CO₂ emissions every year, supporting Tata Power Renewables’ clean energy initiatives.
During construction, the project faced a major change in grid connectivity, converting the extra high voltage (EHV) line configuration from underground cable to monopole, marking the first monopole EHV line installation by Tata Power Renewables’ Wind Project Execution Division.
Despite the mid-project design change, the team maintained the schedule without delay.
With this commissioning, Tata Power Renewables’ total utility renewable capacity has reached 12.1 GW, including 7.3 GW operational capacity comprising 5.9 GW solar and 1.4 GW wind, plus 4.8 GW under implementation.
Highlights
- 100.8 MW wind project commissioned in Ausa, Maharashtra by Tata Power Renewables.
- Annual generation expected: 308 million units of clean electricity.
- CO₂ emissions reduction estimated at 252,560 tonnes per year.
- First monopole extra high voltage (EHV) line installation for a wind project by Tata Power Renewables.
- Project supplies renewable power to Tata Power Mumbai Distribution (TPC-D).
- Tata Power Renewables’ total renewable utility capacity now 12.1 GW with 7.3 GW operational.
Key Data Snapshot
What happened
- Tata Power Renewable Energy Limited commissioned a 100.8 MW wind energy project in Ausa, Maharashtra.
- The project contributes renewable power to Tata Power Mumbai Distribution (TPC-D).
- It is expected to generate approximately 308 million units of electricity annually.
- The project supports reducing around 252,560 tonnes of CO₂ emissions each year.
Key details
- Project consists of 28 Horizontal Axis Wind Turbine Generators (model SG 3.6-145).
- Midway, the project shifted its grid connectivity from underground cable to monopole EHV line, a first for TPREL’s Wind Project Execution Division.
- Despite the design change, project execution timeline was maintained without delays.
Operational performance
- The project adds to Tata Power Renewables’ total utility capacity reaching 12.1 GW.
- Currently, 7.3 GW of this capacity is operational, including 5.9 GW solar and 1.4 GW wind energy.
- An additional 4.8 GW renewable capacity is under various implementation stages.
Background and context
- Tata Power is a vertically integrated power company part of the Tata Group, with a total capacity exceeding 27 GW.
- Its portfolio includes 18.3 GW clean energy and 8.8 GW thermal generation capacity.
- Tata Power operates extensive transmission and distribution networks serving over 13 million customers.
- It is also involved in solar cell and module manufacturing, pumped hydro storage projects, and EV charging infrastructure expansion.
Highlights
- 100.8 MW wind project commissioned in Ausa, Maharashtra by Tata Power Renewables.
- Annual generation expected: 308 million units of clean electricity.
- CO₂ emissions reduction estimated at 252,560 tonnes per year.
- First monopole extra high voltage (EHV) line installation for a wind project by Tata Power Renewables.
- Project supplies renewable power to Tata Power Mumbai Distribution (TPC-D).
- Tata Power Renewables’ total renewable utility capacity now 12.1 GW with 7.3 GW operational.
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015
More News on Capacity Expansion
View allLatest corporate announcements and market updates in Capacity Expansion.
Juniper Green Energy Raises Operational Capacity to 2,952 MWp with Commissioning of 108.50 MWp Solar Component in Hybrid Project
Juniper Green Energy Limited announced that its wholly owned subsidiary Juniper Green ETA Five Private Limited has commissioned 108.50 MWp of solar capacity as part of a 75 MW wind-solar hybrid power project with Maharashtra State Electricity Distribution Company Limited on November 19, 2026.
Read Full StoryJuniper Green Energy Subsidiary Commissions 94.77 MWh Battery Energy Storage System on November 19, 2026
Juniper Green Stellar Private Limited, a wholly owned subsidiary of Juniper Green Energy Limited, has commissioned a 94.77 MWh Battery Energy Storage System on November 19, 2026. This capacity is currently deployed as a merchant capacity with flexibility to convert to a long-term Power Purchase Agreement in the future.
Read Full StoryACME Solar Holdings Commissions 155.71 MW Renewable Energy Project With Battery Storage in Rajasthan
ACME Solar Holdings Limited announced commissioning 155.71 MW of its Firm and Dispatchable Renewable Energy project in Rajasthan, comprising a 100.02 MW solar plant and a 55.69 MW battery energy storage system, on November 19, 2026, with commercial operations starting from November 21, 2026.
Read Full Story