Tata Power Approves ₹11,871 Crore Investment to Add 1,800 MW Pumped Storage Hydro Project in Maharashtra
The project will expand Tata Power's capacity from 16.9 GW and support renewable energy round-the-clock applications within 51 months of development
Tata Power's Board approves an investment of ₹11,871 crore for a 1,800 MW Pumped Storage Project at Shirwata, Maharashtra, planned to be completed in 51 months with 75% debt and 25% equity financing, expanding its total capacity from 16.9 GW to support renewable energy reliability and decarbonization efforts.
The Tata Power Company Limited
Capacity Expansion
Tata Power's Board of Directors has approved an investment of ₹11,871 crore to develop a new 1,800 MW Pumped Storage Project at Shirwata, Maharashtra, scheduled for completion within 51 months, expanding the company's total capacity beyond its current 16.9 GW.
The investment will be financed with 75% debt and 25% equity, supporting sustainable funding structure for the project.
This Pumped Storage Hydro Project aims to enhance renewable energy round-the-clock (RE-RTC) capabilities by enabling energy shifting and aiding decarbonization of industries that are difficult to electrify.
The capacity utilization of Tata Power's existing assets currently stands at optimum levels, supporting the feasibility of adding new generation capacity.
Project details and progress updates will be made publicly available on Tata Power’s official website.
Highlights
- Existing Tata Power capacity is 16.9 GW with optimum utilization.
- New Pumped Storage Project capacity: 1,800 MW at Shirwata, Maharashtra.
- Investment required: ₹11,871 crore.
- Financing mix: 75% debt, 25% equity.
- Project timeline: Completion within 51 months.
- Project supports Renewable Energy Round The Clock (RE-RTC) applications.
Key Data Snapshot
What happened
- Tata Power approved an investment in a 1,800 MW Pumped Storage Project at Shirwata, Maharashtra.
- The project aims to support renewable energy round-the-clock and decarbonize difficult-to-electrify industries.
- The new capacity addition will raise the company’s total installed capacity from 16.9 GW.
Key details
- Investment amount is ₹11,871 crore.
- Project will be financed with 75% debt and 25% equity.
- Timeline for project completion is 51 months.
- Existing capacity utilization at Tata Power is at an optimum level.
Strategic context
- Pumped Storage Hydro Project facilitates energy shifting necessary for renewable energy integration.
- Supports Renewable Energy Round The Clock applications to enhance grid stability.
- Contributes to Tata Power’s sustainability and decarbonization initiatives for hard to abate industries.
Regulatory and governance context
- Disclosure made in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
- Details aligned with SEBI master circular dated January 30, 2026.
Highlights
- Existing Tata Power capacity is 16.9 GW with optimum utilization.
- New Pumped Storage Project capacity: 1,800 MW at Shirwata, Maharashtra.
- Investment required: ₹11,871 crore.
- Financing mix: 75% debt, 25% equity.
- Project timeline: Completion within 51 months.
- Project supports Renewable Energy Round The Clock (RE-RTC) applications.
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015
- SEBI Master Circular HO/49/14/14(7)2025- CFD-POD2/I/3762/2026 dated January 30, 2026
More News on Capacity Expansion
View allLatest corporate announcements and market updates in Capacity Expansion.
Juniper Green Energy Raises Operational Capacity to 2,952 MWp with Commissioning of 108.50 MWp Solar Component in Hybrid Project
Juniper Green Energy Limited announced that its wholly owned subsidiary Juniper Green ETA Five Private Limited has commissioned 108.50 MWp of solar capacity as part of a 75 MW wind-solar hybrid power project with Maharashtra State Electricity Distribution Company Limited on November 19, 2026.
Read Full StoryJuniper Green Energy Subsidiary Commissions 94.77 MWh Battery Energy Storage System on November 19, 2026
Juniper Green Stellar Private Limited, a wholly owned subsidiary of Juniper Green Energy Limited, has commissioned a 94.77 MWh Battery Energy Storage System on November 19, 2026. This capacity is currently deployed as a merchant capacity with flexibility to convert to a long-term Power Purchase Agreement in the future.
Read Full StoryACME Solar Holdings Commissions 155.71 MW Renewable Energy Project With Battery Storage in Rajasthan
ACME Solar Holdings Limited announced commissioning 155.71 MW of its Firm and Dispatchable Renewable Energy project in Rajasthan, comprising a 100.02 MW solar plant and a 55.69 MW battery energy storage system, on November 19, 2026, with commercial operations starting from November 21, 2026.
Read Full Story