Pace Digitek Wins Rs. 2,691 Crore 600 MW BESS EPC Contract from NTPC Green Energy for Gujarat Solar Project

Order includes supply, system integration, installation, testing, commissioning, civil works and 15-year O&M for 1800 MWh BESS at Khavda Solar Plant

Pace Digitek Limited has won its largest-ever Battery Energy Storage System (BESS) order worth Rs. 2,691 crore from NTPC Green Energy Limited (NGEL) for engineering, procurement, construction and 15-year operations & maintenance of a 600 MW / 1800 MWh BESS at Khavda Solar Plant, Gujarat. This EPC contract covers Block-01 and Block-02 of the 3300 MWh flagship project, boosting the company's executable order book to Rs. 13,427 crore as of FY2027.

1 day ago|PACEDIGITK-0.21%
Pace Digitek Limited544550PACEDIGITKOrder Wins

Pace Digitek Limited

Order Wins

Pace Digitek Limited has secured a landmark Rs. 2,691 crore order from NTPC Green Energy Limited for the EPC and long-term operation of a 600 MW / 1800 MWh Battery Energy Storage System at the Khavda Solar Plant in Gujarat, marking its largest BESS contract to date.

The order covers Blocks 01 and 02 of the flagship 3300 MWh BESS Project, involving system supply, integration, installation, testing, commissioning, civil works and 15-year operations and maintenance responsibilities.

With this award, Pace Digitek's executable order book has increased to Rs. 13,427 crore, supported by a consolidated BESS project portfolio of 6.62 GWh across EPC and BOO/BOOT models.

The company met the Class-I Local Supplier criteria, requiring a minimum 50% local content, supported by 5 GWh of operational domestic manufacturing capacity and its own container fabrication facility, enhancing its competitiveness.

Pace Digitek has invested in expanding manufacturing capacity towards 10 GWh, supporting growing demand in India's energy storage market.

The order will bolster the company’s manufacturing-led growth and project execution scale in the energy storage ecosystem across India.

Highlights

  • Rs. 2,691 crore EPC contract from NTPC Green Energy Limited for 600 MW / 1800 MWh BESS project.
  • Contract includes supply, integration, installation, commissioning, civil works and 15-year O&M at Khavda Solar Plant, Gujarat.
  • Order covers two 300 MW / 900 MWh blocks under Cluster-01 of the 3300 MWh flagship BESS project.
  • Boosts executable order book to Rs. 13,427 crore for FY2027 with cumulative order inflows of Rs. 5,129 crore.
  • Class-I Local Supplier with minimum 50% local content requirement met, backed by 5 GWh manufacturing capacity.
  • Pace Digitek expanding manufacturing capacity towards 10 GWh for growing market demand.

Key Data Snapshot

Order valueRs. 2,691 crore inclusive of GST
BESS capacity awarded600 MW / 1800 MWh
Project locationNTPC REL Khavda Solar Plant, Gujarat
Contract scopeSystem supply, integration, installation, testing, commissioning, civil works and 15-year O&M
Blocks includedBlock-01 and Block-02 (each 300 MW / 900 MWh)
Executable order book post-awardRs. 13,427 crore
FY2027 cumulative order inflowsRs. 5,129 crore
Consolidated BESS portfolio6.62 GWh across EPC and BOO/BOOT models
Domestic manufacturing capacity operational5 GWh
Manufacturing capacity target10 GWh

What happened

  • Pace Digitek secured a Rs. 2,691 crore EPC contract from NTPC Green Energy Limited for a 600 MW / 1800 MWh Battery Energy Storage System.
  • The scope includes end-to-end delivery from supply, integration, installation, commissioning to civil works plus 15 years of operations and maintenance.
  • This contract covers Blocks-01 and -02 of the 3300 MWh flagship BESS project at the NTPC REL Khavda Solar Plant in Gujarat.

Key details

  • The order is Pace Digitek’s largest BESS contract to date and enhances its executable order book to Rs. 13,427 crore as of FY2027.
  • The combined manufacturing capacity involved is supported by 5 GWh of domestic BESS manufacturing and in-house container fabrication facilities, meeting Class-I Local Supplier requirements.
  • The project advances Pace Digitek’s presence and scale in India’s energy storage ecosystem.

Strategic context

  • Class-I Local Supplier status requiring minimum 50% local content strengthened bid competitiveness.
  • Expansion plans to increase manufacturing capacity to 10 GWh aim to support growing demand in India's energy storage sector.
  • The contract provides long-term revenue visibility with 15 years of operations and maintenance included.

More News on Order Wins

View all

Latest corporate announcements and market updates in Order Wins.

View all news
Pace Digitek Wins Rs. 2,691 Crore 600 MW BESS EPC | Stockk News