Waaree Energies Confirms Proper Use of Rs. 3600 Crore IPO Funds with Project Relocation Approval for Q2 2026

Monitoring Agency CARE Ratings finds no deviation in fund utilization; shareholders approved shifting manufacturing projects to Gujarat and Maharashtra

Waaree Energies Limited disclosed its Monitoring Agency Report for the quarter ended September 30, 2026, confirming no deviations in the utilization of Rs. 3600 crore raised through its IPO. The company informed shareholders about approved relocation of project sites from Odisha to Gujarat and Maharashtra, with deployment timelines updated accordingly. Proceeds remain mostly parked in term deposits with scheduled banks pending investment in projects.

7 days ago|WAAREEENER+0.58%
Waaree Energies LtdWAAREEENERCorporate Action

Waaree Energies Ltd

Corporate Action

Waaree Energies Limited has reported through CARE Ratings, its monitoring agency, that there have been no deviations in the utilization of Rs. 3600 crore raised via its IPO for the quarter ended September 30, 2026. The company has updated key project locations with necessary shareholder approval.

Waaree Energies raised Rs. 3600 crore from its initial public offering conducted from October 21 to October 23, 2024, intending to use the funds for solar manufacturing projects.

The monitoring agency report confirms that funds have been partially utilized as per the IPO's disclosed objectives, with the remainder held in term deposits with scheduled commercial banks, primarily under the subsidiary names where projects are being developed.

The company changed its project location from Odisha to Gujarat for solar cell and module manufacturing, and to Maharashtra for ingot-wafer manufacturing. This change was approved by shareholders via postal ballot on August 1, 2025.

The total cost of establishing these plants remains consistent with the original objects of the IPO.

Deployment timelines for fund utilization have been revised to reflect project changes, initially scheduled for Rs. 275 crore by March 31, 2025, and Rs. 2000 crore by March 31, 2026, now postponed according to the revised completion dates.

Highlights

  • IPO raised Rs. 3600 crore between October 21-23, 2024
  • No deviation from utilization of issue proceeds as per CARE Ratings report for Q2 2026
  • Funds mostly parked as term deposits with scheduled banks pending deployment
  • Shareholders approved relocation of projects from Odisha to Gujarat and Maharashtra on August 1, 2025
  • Revised timelines postpone fund deployment beyond original March 2025 and 2026 deadlines
  • 6 GW solar module manufacturing lines at Samakhiali, Gujarat became fully operational from April 6, 2026

Key Data Snapshot

IPO funds raisedRs. 3600 crore
IPO issue periodOctober 21-23, 2024
Monitoring report periodQuarter ended September 30, 2026
Project location changes approvedFrom Odisha to Gujarat and Maharashtra
Shareholder approval dateAugust 1, 2025
Solar module manufacturing capacity operational dateApril 6, 2026
Scheduled fund deployment targetsRs. 275 crore by March 31, 2025; Rs. 2000 crore by March 31, 2026 (postponed)

What happened

  • Waaree Energies raised Rs. 3600 crore through a public IPO in October 2024 for solar manufacturing projects.
  • A monitoring report by CARE Ratings for Q2 2026 confirmed no deviations in utilization of these IPO proceeds.
  • Funds are partially deployed with remainder parked as term deposits in scheduled commercial banks.
  • The company changed key project manufacturing locations, approved by shareholders in August 2025.
  • Revised timelines postponed major fund deployment beyond earlier set dates due to project changes.

Key details

  • Monitoring Agency is CARE Ratings Limited, engaged under SEBI regulations.
  • Funds have been invested or parked under subsidiary names for respective projects.
  • Shareholders approved relocation of solar cell and module plants to Gujarat, and ingot-wafer manufacturing to Maharashtra via postal ballot.
  • Company provided Board-approved policy for investment of IPO proceeds in term deposits for up to three years.
  • 6 GW solar module manufacturing line at Samakhiali, Gujarat has been fully operational since April 6, 2026.

Regulatory and governance context

  • Monitoring report prepared in compliance with SEBI Listing Obligations and Disclosure Requirements and Issue of Capital and Disclosure Requirements regulations.
  • No deviation or material change in financing means for disclosed IPO objects.
  • Shareholder approval obtained for material project location changes as per regulatory requirements.
  • Monitoring agency does not perform audit but relies on information certified by the company.
  • Company continues to comply with government and statutory approvals relevant to the projects.