Trident Limited Approves INR 4,650 Crore Capacity Expansion and Modernisation Project
Project includes new yarn facilities in Madhya Pradesh, sheeting business expansion, paper capacity increase, and 80 MW hybrid renewable energy setup
Trident Limited's board has approved a major INR 4,650 Crore capacity expansion and modernisation project including yarn spindle addition, a new facility in Dhar, and renewable energy initiatives to enhance production capacities and sustainability.
Trident Limited
Financial Results
Trident Limited's board approved a INR 4,650 Crore project to expand and modernise its production capacities, including yarn spindle additions at Budhni, a new yarn facility at Dhar, enhancements in sheeting and paper manufacturing, and a hybrid renewable energy project.
The expansion includes adding 99,840 spindles at the existing Budhni yarn manufacturing facility, modernising 48,000 older spindles to 70,176 new finer count spindles, and replacing 960 old rotors with 2,400 new rotors.
A new yarn manufacturing unit with a capacity of 1,99,680 spindles will be established at Dhar, Madhya Pradesh, for which the company has acquired 179.2 acres of leasehold land at approximately INR 106.09 Crores.
The sheeting business will be expanded by adding 336 looms, while paper manufacturing capacity will be increased by 28 TPD (tons per day).
To support sustainable operations and improve energy efficiency, the company will set up a 60 MW hybrid renewable energy project including 60 MW wind power and 20 MW solar power (AC).
Highlights
- Total investment: INR 4,650 Crores for capacity expansion and modernisation.
- Budhni facility: Addition of 99,840 spindles and modernisation of older equipment.
- New facility: Yarn manufacturing at Dhar with 1,99,680 spindles capacity on 179.2 acres.
- Sheeting business: Addition of 336 looms.
- Paper manufacturing: Capacity increased by 28 TPD.
- Renewable energy project: 60 MW wind power and 20 MW solar power to enhance sustainability.
Key Data Snapshot
What happened
- Trident Limited's board approved a capacity expansion and modernisation project costing INR 4,650 Crores.
- The project covers multiple business segments including yarn manufacturing, sheeting, paper manufacturing, and renewable energy.
- The Board meeting was held on November 2, 2026 and lasted from 10:30 A.M. to 4:00 P.M. IST.
Key details
- At Budhni, MP, 99,840 new yarn spindles will be added, with significant modernisation of existing equipment.
- A new yarn manufacturing facility with 1,99,680 spindles will be set up at Dhar, MP, with land acquisition already completed.
- Sheeting business will be expanded by adding 336 looms, and paper manufacturing capacity increased by 28 TPD.
- A 60 MW wind and 20 MW solar hybrid renewable energy project will be established to support sustainable operations.
Regulatory and governance context
- The financial results for the quarter and half year ended September 30, 2026, have been approved and subjected to limited audit review.
- The statutory auditor is M/s S.R. Batliboi & Co. LLP, Chartered Accountants.
- The company complies with SEBI Listing Regulations and Indian Accounting Standards for interim financial reporting.
Highlights
- Total investment: INR 4,650 Crores for capacity expansion and modernisation.
- Budhni facility: Addition of 99,840 spindles and modernisation of older equipment.
- New facility: Yarn manufacturing at Dhar with 1,99,680 spindles capacity on 179.2 acres.
- Sheeting business: Addition of 336 looms.
- Paper manufacturing: Capacity increased by 28 TPD.
- Renewable energy project: 60 MW wind power and 20 MW solar power to enhance sustainability.
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015
- Indian Accounting Standard 34 (Ind AS 34)
More News on Financial Results
View allLatest corporate announcements and market updates in Financial Results.
Lloyds Engineering Posts 110% Revenue Growth and Rs. 4,591.67 Crore Order Book in H1 FY2027
Lloyds Engineering Works Limited declared its unaudited financial results for the quarter and half year ended September 30, 2026, reporting a consolidated revenue of Rs. 1,120.70 crore, an increase of approximately 110% over the previous equivalent period, alongside a substantial rise in its consolidated order book position to Rs. 4,591.67 crore as of October 1, 2026.
Read Full StoryNational Aluminium Company Reports Q2 2026 Unaudited Financial Results and Declares Rs.4.50 Interim Dividend per Share for FY 2026-27
National Aluminium Company Limited announced its unaudited standalone and consolidated financial results for the second quarter and half year ended 30th September 2026. The board also approved an interim dividend of Rs.4.50 per share for the financial year 2026-27, payable to shareholders registered by 6th November 2026.
Read Full StoryVentive Hospitality Announces Q2 and H1 FY2027 Unaudited Results and Rs. 200 Crore Loan Support for Subsidiary
Ventive Hospitality Limited released its unaudited standalone and consolidated financial results for the quarter and half year ended September 30, 2026, and approved a Letter of Comfort to ICICI Bank for a Rs. 200 crore loan facility for its wholly owned subsidiary KBJ Hotel & Restaurants Private Limited.
Read Full Story