SJVN Commissions Second 660 MW Unit of Buxar Thermal Power Project, Reaching Full 1320 MW Capacity

Prime Minister Modi dedicates the ₹7,221.09 crore second unit virtually, completing the project with ₹14,269.40 crore total cost and 85% power allocated to Bihar

SJVN Limited's wholly-owned subsidiary dedicated the second 660 MW unit of the 1320 MW Buxar Thermal Power Project in Bihar, completing the full capacity of the strategically important coal-based energy infrastructure. The project, costing ₹14,269.40 crore, uses Ultra Super Critical Technology to generate approximately 9,828.72 million units annually, with 85% power allocated to Bihar under long-term agreements, enhancing the region's power reliability and economic growth.

20 hours ago|SJVN+0.00%
SJVN LimitedSJVNCapacity Expansion

SJVN Limited

Capacity Expansion

SJVN Limited marked a significant milestone as Prime Minister Narendra Modi virtually dedicated the second 660 MW unit of the 1320 MW Buxar Thermal Power Project in Bihar, finalizing the project’s full commissioning with an investment of ₹7,221.09 crore for this unit.

The Buxar Thermal Power Project is located at Chausa in Buxar district, Bihar, and is developed by SJVN's wholly-owned subsidiary, SJVN Thermal Private Limited (STPL). The project features two units of 660 MW each, designed to generate roughly 9,828.72 million units of energy annually at an 85% Plant Load Factor.

The total approved revised cost of the project stands at ₹14,269.40 crore. The first unit was inaugurated on 22 August 2025, with the foundation stone laid on 9 March 2019 by Prime Minister Modi. The project utilizes Ultra Super Critical Technology with modern emission control systems to enhance operational efficiency and reduce environmental impact.

A Fuel Supply Agreement has been signed with Central Coalfields Limited (CCL), ensuring long-term linkage of domestic coal. About 85% of the electricity generated is allocated to Bihar under a long-term Power Purchase Agreement, aiding the state's energy demands during peak periods and supporting industrial, agricultural, commercial, and residential consumption.

The construction phase engaged around 65,000 workers, utilizing over 2,54,932 MT of steel and 2,84,291 MT of cement sourced domestically, aligning with the Government of India's Atmanirbhar Bharat initiative. The project also supports local socio-economic development through corporate social responsibility programs in affected communities.

Highlights

  • Second 660 MW unit of Buxar Thermal Power Project dedicated by Prime Minister Narendra Modi on 21 November 2026.
  • Total project capacity is 1320 MW with two units of 660 MW each.
  • Investment for second unit is ₹7,221.09 crore; total revised project cost is ₹14,269.40 crore.
  • Annual planned energy generation is approximately 9,828.72 million units at 85% Plant Load Factor.
  • 85% of generated power allocated to Bihar under a long-term Power Purchase Agreement.
  • Project employs Ultra Super Critical Technology with modern emission control systems to reduce environmental impact and increase efficiency.

Key Data Snapshot

Second unit capacity660 MW
Total project capacity1320 MW (2×660 MW)
Investment in second unit₹7,221.09 crore
Total approved revised cost of project₹14,269.40 crore
Annual energy generation9,828.72 million units
Plant Load Factor85%
Steel used in construction2,54,932 MT
Cement used in construction2,84,291 MT
Workers engaged during constructionApproximately 65,000
Power allocation to Bihar85% under long-term Power Purchase Agreement

What happened

  • The second 660 MW unit of the 1320 MW Buxar Thermal Power Project was dedicated to the nation virtually by Prime Minister Narendra Modi on 21 November 2026.
  • This event completes the commissioning of the project’s full capacity.
  • The project is developed by SJVN Thermal Private Limited, a wholly-owned subsidiary of SJVN Limited.
  • The total revised investment cost of the project is ₹14,269.40 crore.

Key details

  • Buxar Thermal Power Project is located at Chausa in Buxar district, Bihar.
  • The project includes two units of 660 MW each using Ultra Super Critical Technology and modern emission control.
  • The first unit was inaugurated on 22 August 2025; the foundation stone was laid on 9 March 2019 by the Prime Minister.
  • The plant is designed to generate approximately 9,828.72 million units of electricity annually at an 85% Plant Load Factor.
  • A Fuel Supply Agreement for coal linkage has been executed with Central Coalfields Limited (CCL).
  • Approximately 85% of generated power is allocated to Bihar under a long-term Power Purchase Agreement.

Business impact

  • The project will support Bihar’s growing electricity requirements, especially during peak demand periods, strengthening the reliability and stability of the Eastern Regional Power Grid.
  • Power generated will aid industrial activities, agriculture, commercial establishments, and households in Bihar and nearby regions.
  • The construction involved significant use of domestically sourced materials, supporting the Government of India's Atmanirbhar Bharat vision.
  • About 65,000 workers were engaged during construction, generating employment and supporting local livelihoods.
  • Ongoing Corporate Social Responsibility initiatives promote socio-economic development in project-affected communities.

Background and context

  • SJVN Limited is a Navratna CPSE and joint venture of Govt. of India and Govt. of Himachal Pradesh, incorporated on 24 May 1988.
  • SJVN has an installed capacity of 4,931.50 MW with 3,860.50 MW under construction across India and Nepal, contributing to national energy security and sustainable development.