Dirang Energy Private Limited awards contract for construction and execution of hydroelectric project with a 48-month timeline

Patel Engineering Limited has been declared the lowest bidder and awarded a ₹1,441.04 crore contract by its subsidiary Dirang Energy Private Limited for the 144 MW Gongri Hydro Electric Project in Arunachal Pradesh. The project includes extensive hydro-mechanical and electro-mechanical works and is scheduled for completion within 48 months.

55 mins ago|PATELENG+3.96%
Patel Engineering Ltd.PATELENGOrder Wins

Patel Engineering Ltd.

Order Wins

Patel Engineering Limited has been awarded a ₹1,441.04 crore contract by its wholly owned subsidiary, Dirang Energy Private Limited, to execute the 144 MW Gongri Hydro Electric Project in West Kameng district, Arunachal Pradesh, scheduled for completion within 48 months.

Dirang Energy Private Limited, a special purpose company established by Patel Engineering, selected Patel Engineering as the lowest bidder (L1) for the project valued at ₹1,441.04 crore including GST.

The Gongri Hydro Electric Project comprises two 72 MW units, with a design annual energy generation capacity of 623.19 million units, assuming a 90% dependable water flow and 95% plant availability.

The project scope includes construction of a diversion barrage with four radial gates, intake structures, two desilting chambers, a 7.1 km long head race tunnel (5.8 m diameter), a surge shaft (13 m diameter), and a pressure shaft (4.4 m diameter and 647.26 m long).

Additional components encompass the surface powerhouse, tail race channel for water return, switchyard, and hydro-mechanical and electro-mechanical works.

The project will be developed on a Build-Own-Operate-Transfer (BOOT) basis for a 40-year lease period, supporting renewable power generation in Arunachal Pradesh.

Highlights

  • Contract awarded on November 26, 2026, valued at ₹1,441.04 crore including GST.
  • Project capacity of 144 MW with two 72 MW units.
  • Construction period set at 48 months from award date.
  • Located in West Kameng district, Arunachal Pradesh on the Gongri River.
  • Project includes major civil, hydro-mechanical and electro-mechanical works.
  • Designed to generate 623.19 million units annually under 90% dependable flow and 95% availability conditions.

Key Data Snapshot

Contract Value₹ 1441.04 Crores (Including GST)
Project Capacity144 MW (2 x 72 MW)
Project LocationWest Kameng District, Arunachal Pradesh
Contract Award DateNovember 26, 2026
Project Completion Period48 months
Annual Energy Design623.19 million units (MU)
Water Flow Dependability90%
Plant Availability95%
Project TypeRun-of-the-river hydroelectric

What happened

  • Patel Engineering Limited was awarded the lowest bidder contract to execute the 144 MW Gongri Hydro Electric Project by its subsidiary Dirang Energy Private Limited.
  • The contract value is ₹1,441.04 crore including GST with a 48-month construction timeline.
  • The project is a run-of-the-river hydroelectric plant located on the Gongri River in Arunachal Pradesh.

Key details

  • The project includes construction of diversion barrages, intake structures, desilting chambers, long tunnels, surge and pressure shafts, a surface powerhouse, and switchyard.
  • Hydro-mechanical and electro-mechanical works form part of the contract scope.
  • The estimated annual energy generation is 623.19 million units with a 40-year BOOT lease arrangement.

Transaction details

  • The order was awarded by Dirang Energy Private Limited, a wholly owned subsidiary of Patel Engineering.
  • The contract is a domestic transaction valued at ₹1,441.04 crore including GST.
  • The contract falls under related party transactions but is executed on an arm’s length basis.

Strategic context

  • This project supports clean, renewable power production in Arunachal Pradesh.
  • The Build-Own-Operate-Transfer basis plan extends over a 40-year lease period.
  • The project leverages Patel Engineering’s expertise in hydropower and infrastructure.