NHPC Limited Reports 14% Increase in Power Generation and 27% PAT Growth in H1 FY27

Subansiri Lower Project reaches 1,250 MW commissioned, with further units planned in FY27; company’s revenue rises 26% to Rs. 8,291 crore

NHPC Limited announced a 14% increase in power generation to 23,741 MUs and a 27% rise in PAT to Rs. 2,645 crore for the half year ended September 30, 2026, driven by commissioning progress in key projects including Subansiri Lower and resumption of Teesta-V operations. The company also detailed project statuses and expenditure on major hydroelectric initiatives like Dibang Multipurpose and Teesta-VI.

6 days ago|NHPC-0.71%
NHPC Limited533098NHPCEarnings Call Transcript

NHPC Limited

Earnings Call Transcript

NHPC Limited reported power generation of 23,741 MUs for the half year ended September 30, 2026, marking a 14% increase over the previous year, accompanied by a 27% rise in profit after tax to Rs. 2,645 crore. The increase was supported by the commissioning of units in the Subansiri Lower Project and resumption of commercial operations at Teesta-V power station.

The company’s Plant Availability Factor (PAF) improved from 81.10% to 86.67% during H1 FY27, reflecting better operational performance mainly due to new unit commissioning and resumption of operations.

Revenue from operations was Rs. 8,291 crore, up 26% from Rs. 6,579 crore in the corresponding previous period.

In the Subansiri Lower Project, five out of eight 250 MW units (total 1,250 MW) have been commissioned as of October 23, 2026. Two more units are planned to be commissioned within the current financial year and the final unit by June 2027. The projected cost is Rs. 30,072 crore, with 90% of this spent by September 2026.

The Dibang Multipurpose Project (2,880 MW) has all major contracts awarded and key milestones like Nalla diversion achieved. Its estimated cost is Rs. 31,876 crore with Rs. 5,504 crore spent to date. The project is targeted for completion by February 2032.

Teesta-VI Hydroelectric Project (500 MW) shows 74% physical progress, with an estimated cost of Rs. 9,167 crore and Rs. 5,650 crore spent till September 2026. Commissioning is expected by September 2029 despite tunneling challenges currently faced.

Highlights

  • Power generation rose 14% to 23,741 MUs in H1 FY27.
  • Profit after tax increased by 27% to Rs. 2,645 crore.
  • PAF improved to 86.67% from 81.10%.
  • Subansiri Lower Project commissioned 1,250 MW out of 2,000 MW with 90% cost incurred.
  • Dibang Multipurpose Project progressing, targeted for February 2032 completion.
  • Teesta-VI HEP at 74% completion, commissioning expected September 2029.

Key Data Snapshot

Power Generation23,741 MUs
Power Generation Previous Period20,866 MUs
PAT H1 FY27Rs. 2,645 Crore
PAT Previous PeriodRs. 2,086 Crore
Revenue from Operations H1 FY27Rs. 8,291 Crore
Revenue Previous PeriodRs. 6,579 Crore
PAF H1 FY2786.67%
PAF Previous Period81.10%
Subansiri Lower Project Capacity Commissioned1,250 MW
Subansiri Lower Project Estimated CostRs. 30,072 Crore
Subansiri Lower Project Cost IncurredRs. 26,936 Crore
Dibang Multipurpose Project Capacity2,880 MW
Dibang Project Estimated CostRs. 31,876 Crore
Dibang Project Cost IncurredRs. 5,504 Crore as of Sept 2026

What happened

  • NHPC Limited increased power generation by 14% to 23,741 MUs during H1 FY27 compared to the previous year.
  • Profit after tax rose by 27% to Rs. 2,645 crore.
  • Revenue from operations rose by 26% to Rs. 8,291 crore.
  • Plant Availability Factor (PAF) improved to 86.67% from 81.10%.

Key details

  • Subansiri Lower Hydroelectric Project commissioned 5 out of 8 units totaling 1,250 MW, with two more units expected in FY27 and completion by June 2027.
  • The Subansiri project’s total estimated cost is Rs. 30,072 crore, with 90% spent to date; no cost overrun anticipated.
  • Dibang Multipurpose Project contracts awarded; Nalla diversion completed; cost estimated at Rs. 31,876 crore with Rs. 5,504 crore spent; completion planned for February 2032.
  • Teesta-VI Hydroelectric Project 74% physically complete; Rs. 9,167 crore estimated cost and Rs. 5,650 crore spent; commissioning expected by September 2029 despite tunneling challenges.

Background and context

  • The company’s improved power generation is supported by commissioning of new units in key projects including Subansiri Lower and resumption of operations at Teesta-V.
  • NHPC’s ongoing investment and project developments indicate focus on expanding hydroelectric capacity.

More News on Earnings Call Transcript

View all

Latest corporate announcements and market updates in Earnings Call Transcript.

View all news
NHPC Limited Reports 14% Increase in Power Generation | Stockk News