NHPC Limited Reports 14% Increase in Power Generation and 27% PAT Growth in H1 FY27
Subansiri Lower Project reaches 1,250 MW commissioned, with further units planned in FY27; company’s revenue rises 26% to Rs. 8,291 crore
NHPC Limited announced a 14% increase in power generation to 23,741 MUs and a 27% rise in PAT to Rs. 2,645 crore for the half year ended September 30, 2026, driven by commissioning progress in key projects including Subansiri Lower and resumption of Teesta-V operations. The company also detailed project statuses and expenditure on major hydroelectric initiatives like Dibang Multipurpose and Teesta-VI.
NHPC Limited
Earnings Call Transcript
NHPC Limited reported power generation of 23,741 MUs for the half year ended September 30, 2026, marking a 14% increase over the previous year, accompanied by a 27% rise in profit after tax to Rs. 2,645 crore. The increase was supported by the commissioning of units in the Subansiri Lower Project and resumption of commercial operations at Teesta-V power station.
The company’s Plant Availability Factor (PAF) improved from 81.10% to 86.67% during H1 FY27, reflecting better operational performance mainly due to new unit commissioning and resumption of operations.
Revenue from operations was Rs. 8,291 crore, up 26% from Rs. 6,579 crore in the corresponding previous period.
In the Subansiri Lower Project, five out of eight 250 MW units (total 1,250 MW) have been commissioned as of October 23, 2026. Two more units are planned to be commissioned within the current financial year and the final unit by June 2027. The projected cost is Rs. 30,072 crore, with 90% of this spent by September 2026.
The Dibang Multipurpose Project (2,880 MW) has all major contracts awarded and key milestones like Nalla diversion achieved. Its estimated cost is Rs. 31,876 crore with Rs. 5,504 crore spent to date. The project is targeted for completion by February 2032.
Teesta-VI Hydroelectric Project (500 MW) shows 74% physical progress, with an estimated cost of Rs. 9,167 crore and Rs. 5,650 crore spent till September 2026. Commissioning is expected by September 2029 despite tunneling challenges currently faced.
Highlights
- Power generation rose 14% to 23,741 MUs in H1 FY27.
- Profit after tax increased by 27% to Rs. 2,645 crore.
- PAF improved to 86.67% from 81.10%.
- Subansiri Lower Project commissioned 1,250 MW out of 2,000 MW with 90% cost incurred.
- Dibang Multipurpose Project progressing, targeted for February 2032 completion.
- Teesta-VI HEP at 74% completion, commissioning expected September 2029.
Key Data Snapshot
What happened
- NHPC Limited increased power generation by 14% to 23,741 MUs during H1 FY27 compared to the previous year.
- Profit after tax rose by 27% to Rs. 2,645 crore.
- Revenue from operations rose by 26% to Rs. 8,291 crore.
- Plant Availability Factor (PAF) improved to 86.67% from 81.10%.
Key details
- Subansiri Lower Hydroelectric Project commissioned 5 out of 8 units totaling 1,250 MW, with two more units expected in FY27 and completion by June 2027.
- The Subansiri project’s total estimated cost is Rs. 30,072 crore, with 90% spent to date; no cost overrun anticipated.
- Dibang Multipurpose Project contracts awarded; Nalla diversion completed; cost estimated at Rs. 31,876 crore with Rs. 5,504 crore spent; completion planned for February 2032.
- Teesta-VI Hydroelectric Project 74% physically complete; Rs. 9,167 crore estimated cost and Rs. 5,650 crore spent; commissioning expected by September 2029 despite tunneling challenges.
Background and context
- The company’s improved power generation is supported by commissioning of new units in key projects including Subansiri Lower and resumption of operations at Teesta-V.
- NHPC’s ongoing investment and project developments indicate focus on expanding hydroelectric capacity.
Highlights
- Power generation rose 14% to 23,741 MUs in H1 FY27.
- Profit after tax increased by 27% to Rs. 2,645 crore.
- PAF improved to 86.67% from 81.10%.
- Subansiri Lower Project commissioned 1,250 MW out of 2,000 MW with 90% cost incurred.
- Dibang Multipurpose Project progressing, targeted for February 2032 completion.
- Teesta-VI HEP at 74% completion, commissioning expected September 2029.
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015 Regulation 30
More News on Earnings Call Transcript
View allLatest corporate announcements and market updates in Earnings Call Transcript.
Sunrakshakk Industries India Limited Posts INR 265.17 Crores Revenue with 130% PAT Increase in Q2 FY27
Sunrakshakk Industries India Limited reported its Q2 FY27 financial results with revenue of INR 265.17 crores and a profit after tax of INR 16 crores, reflecting year-on-year growth of 119.20% in revenue and 130.10% in PAT, supported by expansion in its FMCG, FMCG intermediates, and edible segments.
Read Full StoryReligare Enterprises Posts INR 4,717 Crores Income and INR 145 Crores Loss After Tax in H1 FY27, Resumes Lending and Strengthens Board
Religare Enterprises Limited has reported consolidated total income of INR 4,717 crores and a loss after tax of INR 145 crores for the half-year ending September 30, 2026, marking a 19% increase in income year-on-year. The company is transitioning from preparation to execution phase by strengthening its board with RBI-approved promoter and shareholder directors, resuming lending through Religare Finvest, and advancing growth in its core financial services and insurance businesses.
Read Full StoryBlack Box Limited Posts Record Q2 FY27 Revenue of INR 1,936 Crores and Expands Order Backlog to $1.04 Billion
Black Box Limited reported its highest-ever quarterly revenue of INR 1,936 crores for Q2 FY27, marking a 22% year-on-year increase, alongside an 88% year-on-year growth in its order backlog, which reached $1.04 billion as of September 2026. Data center order bookings crossed $250 million during H1 FY27, signaling strong momentum in hyperscale digital infrastructure projects.
Read Full Story