Gillette India to Consolidate Manufacturing at Bhiwadi with Rs. 100 Crore Expense and Rs. 60 Crore Investment
Phased relocation from Baddi to Bhiwadi over 18-24 months expected to generate Rs. 20 Crore annual savings
Gillette India Limited announced the consolidation of its grooming manufacturing operations by relocating from Baddi, Himachal Pradesh to Bhiwadi, Rajasthan. The phased relocation will span 18-24 months and involves a one-time expense of Rs. 100 crores and a capital investment of Rs. 60 crores, aiming to unlock annual savings of Rs. 20 crores to enhance supply chain resilience and sustainability.
Gillette India Limited
Capacity Expansion
Gillette India Limited has approved the consolidation of its grooming manufacturing operations by relocating from Baddi, Himachal Pradesh to Bhiwadi, Rajasthan to create a more resilient and sustainable supply chain.
The transition will be phased over approximately 18 to 24 months and will include the transfer of employees and machinery.
The consolidation will incur a one-time expense of about Rs. 100 crores and a capital investment of around Rs. 60 crores over the next 2 to 3 years.
Upon completion, the company expects to achieve annual cost savings of approximately Rs. 20 crores on an ongoing basis.
This strategic move aligns with Gillette India's long-term vision for sustainable growth and value creation.
Highlights
- Consolidation of manufacturing operations at Bhiwadi, Rajasthan approved.
- Phased relocation from Baddi, Himachal Pradesh over 18-24 months.
- One-time expense of Rs. 100 crores expected over 2-3 years.
- Capital investment planned at approximately Rs. 60 crores.
- Estimated ongoing annual savings of Rs. 20 crores from operational efficiencies.
Key Data Snapshot
What happened
- Gillette India’s Board approved consolidating grooming manufacturing operations to the Bhiwadi unit.
- This will involve relocating operations, employees, and machinery from the Baddi unit.
- The phased relocation is planned over a period of approximately 18 to 24 months.
Key details
- The consolidation will incur a one-time expense of about Rs. 100 crores.
- Capital investment of approximately Rs. 60 crores will be made during the process.
- Upon completion, the consolidation is expected to unlock annual savings of about Rs. 20 crores.
- The strategic move aims to build a more resilient, sustainable, and agile supply chain.
Regulatory and governance context
- Disclosure made under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
- Announcement follows board meeting held on November 17, 2026.
Highlights
- Consolidation of manufacturing operations at Bhiwadi, Rajasthan approved.
- Phased relocation from Baddi, Himachal Pradesh over 18-24 months.
- One-time expense of Rs. 100 crores expected over 2-3 years.
- Capital investment planned at approximately Rs. 60 crores.
- Estimated ongoing annual savings of Rs. 20 crores from operational efficiencies.
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, Regulation 30
More News on Capacity Expansion
View allLatest corporate announcements and market updates in Capacity Expansion.
DISA India Limited Opens New 8,000 sq. Metre Manufacturing Facility in Tumkur to Strengthen Global Operations
DISA India Limited, part of the global Norican group, inaugurated a new 8,000 sq. metre manufacturing facility in Tumkur, Karnataka in November 2026, enhancing its capacity to meet increasing customer demand both domestically and internationally.
Read Full StoryHindustan Zinc Approves INR 80,000 Crore Expansion to Double Metal Production Capacity to 2 MTPA
Hindustan Zinc Limited (HZL), a subsidiary of Vedanta Limited, has approved the HZL 2.0 Growth Program to raise its metal production capacity from the current 1.1 million tonnes per annum (MTPA) to 2.0 MTPA through a capital expenditure of approximately INR 80,000 crore over the next three to five years.
Read Full StoryPOWERGRID Sanctions ₹220.09 Crore for Upgrading Gooty-Tumkur 400kV Line Using HTLS Conductor
India's POWERGRID Committee of Directors on Investment has approved a ₹220.09 Crore investment to reconductor the Gooty-Tumkur (Pavagada) 400kV double circuit transmission line using high-temperature low-sag (HTLS) conductor, with commissioning scheduled for June 10, 2028.
Read Full Story