ESDS Software Solution Confirms Sydney AI Factory Installation Complete and Contracted, Billing to Begin January 2027
All 8,208 NVIDIA GPUs installed in Sydney, with full customer contracts on take-or-pay basis matching payments to Sharon AI under US$1.26 billion 60-month deal
ESDS Software Solution Limited clarifies details about its Sydney AI factory agreement with Sharon AI, confirming all 8,208 GPUs installed, final testing underway, and full capacity contracted on a take-or-pay basis. Billing starts January 2027 with projected monthly profit before costs of about US$9 million from a US$1.26 billion contract over 60 months.
ESDS Software Solution Limited
General / Other
ESDS Software Solution Limited has clarified that its Sydney AI factory project in Australia is progressing as planned. The installation of all 8,208 NVIDIA B300 GPUs is complete and undergoing final testing, with customer contracts fully secured on a take-or-pay basis. Handover to ESDS is expected mid-December 2026 and billing will commence in January 2027.
The company confirmed that the project timeline was mutually revised with Sharon AI, the hardware owner, to complete full system testing before handover, aligning with Sharon AI’s public quarterly results. Monthly payments to Sharon AI and from customers will start simultaneously upon cluster acceptance, avoiding incremental costs due to the adjusted schedule.
ESDS’s contractual commitment to Sharon AI amounts to approximately US$1.26 billion over 60 months, equating to about US$21 million monthly at a fixed rate per GPU hour. Customers are contracted to pay ESDS about US$30 million monthly, yielding an estimated monthly profit before operating costs and taxes of around US$9 million, with post-tax profit currently estimated between US$4 million and US$5 million monthly, representing a margin of roughly 14-17%.
The entire Sydney AI factory capacity is booked on a take-or-pay basis, protecting ESDS from risks of low utilization. Customer contract terms mirror those with Sharon AI, and customers have placed substantial capital upfront, including a US$140 million deposit funding ESDS’s security deposit with Sharon AI.
ESDS's role involves managing a complete service including cluster operations, 24x7 network and security, and GPU-as-a-Service, while Sharon AI owns the hardware and data center. This allows capacity expansion without large capital investment in physical infrastructure by ESDS. The company continues to develop its GPU capabilities in India.
Future updates will be provided upon the Sydney AI factory going live and as required under SEBI regulations. The disclosed rupee figures are approximate conversions from US dollars and may fluctuate with exchange rates, but margins in US dollars remain stable.
Highlights
- All 8,208 NVIDIA B300 GPUs installed and in final testing in Sydney AI factory
- Handover expected mid-December 2026; billing starts January 2027
- Contracted GPU capacity sold on take-or-pay basis matching company's payments to Sharon AI
- US$1.26 billion payment commitment to Sharon AI over 60 months (approx. US$21 million monthly)
- Estimated revenue about US$30 million monthly from customers, with post-tax profit estimated US$4–5 million monthly
- US$140 million deposit placed with Sharon AI funded by customer advances, not company’s own cash
Key Data Snapshot
What happened
- ESDS Software Solution clarified details about the Sydney AI factory project in Australia with Sharon AI.
- All 8,208 NVIDIA GPUs have been installed, and final testing is underway.
- The cluster handover to ESDS is expected in mid-December 2026, with billing starting January 2027.
- The entire GPU capacity is fully contracted on a take-or-pay basis with customers, matching the company's payment obligation to Sharon AI.
Key details
- The project delivery schedule was mutually revised without increasing costs, allowing full testing before handover.
- Contractual commitment is approximately US$1.26 billion over 60 months, about US$21 million per month.
- Customers pay ESDS about US$30 million monthly, resulting in an estimated profit margin of 14-17%.
- Customer advances funded a US$140 million security deposit with Sharon AI; no additional letters of credit or guarantees are outstanding.
- ESDS manages the complete GPU service while Sharon AI owns the hardware and data center capacity.
Regulatory and governance context
- ESDS will continue disclosures required under SEBI Listing Regulations, including updates when the Sydney AI factory goes live.
- Customer contract terms will be disclosed as mandated by regulations.
- Rupee figures provided are approximate conversions from US dollars and subject to exchange rate fluctuations.
Highlights
- All 8,208 NVIDIA B300 GPUs installed and in final testing in Sydney AI factory
- Handover expected mid-December 2026; billing starts January 2027
- Contracted GPU capacity sold on take-or-pay basis matching company's payments to Sharon AI
- US$1.26 billion payment commitment to Sharon AI over 60 months (approx. US$21 million monthly)
- Estimated revenue about US$30 million monthly from customers, with post-tax profit estimated US$4–5 million monthly
- US$140 million deposit placed with Sharon AI funded by customer advances, not company’s own cash
Disclosures
- SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015
Source Information
More News on General / Other
View allLatest corporate announcements and market updates in General / Other.
MobiKwik's Diwali Payments GMV Jumps 80% to INR 3,018 Crore with Major Contributions from Tier 2 and Smaller Cities
One MobiKwik Systems Limited announced an 80% increase in payments gross merchandise value (GMV) during the four-day Diwali festival in 2026, reaching INR 3,018 crore compared to INR 1,678 crore last year. This growth was driven by strong consumer and merchant payment activity, particularly in Tier 2 and smaller cities.
Read Full StoryBharat Parenterals Limited Clarifies No Undisclosed Events Causing Recent Stock Price Changes
Bharat Parenterals Limited officially replied to a BSE inquiry about significant stock price movements, stating no undisclosed information or material events influenced the changes and affirming regulatory compliance.
Read Full StoryKilburn Engineering Promoter Firstview Trading Buys 15,000 Shares in Open Market on November 19, 2026
Kilburn Engineering Limited's promoter, Firstview Trading Private Limited, acquired 15,000 equity shares on November 19, 2026, raising its total stake to 29.59%.
Read Full Story