WhatsApp
backNews Article

Diamond Power Infrastructure Secures Rs. 488.18 Crore Orders from Adani Energy for ±800 kV HVDC Bhadla-Fatehpur Project

6,660 km of AL-59 Lapwing and Zebra conductors to be delivered by December 2027 for Uttar Pradesh and Madhya Pradesh segments

Diamond Power Infrastructure Limited has received two purchase orders valued at Rs. 488.18 crore including GST from Adani Energy Solutions Limited for supplying 6,660 km of AL-59 conductors for the ±800 kV HVDC Bhadla-Fatehpur transmission project covering Uttar Pradesh and Madhya Pradesh. Deliveries are scheduled to complete by December 31, 2027, further strengthening the company's presence in India's HVDC transmission segment.

8 hours ago|DIACABS-4.44%
Diamond Power Infrastructure LimitedBSE:522163NSE:DIACABSOrder Wins

Diamond Power Infrastructure Limited

Order Wins

Diamond Power Infrastructure Limited has received two substantial purchase orders from Adani Energy Solutions Limited worth Rs. 488.18 crore including GST for supplying AL-59 conductors for the ±800 kV HVDC Bhadla-Fatehpur transmission project, covering the Uttar Pradesh and Madhya Pradesh sections.

The orders cover a total of 6,660 km of AL-59 conductors, including 5,693 km of AL-59 Lapwing and 967 km of AL-59 Zebra conductors, to be supplied on a delivered-at-site basis as per project milestones.

The supply contract requires deliveries to be made monthly in accordance with the project schedule, with completion set by December 31, 2027.

This latest order extends Diamond Power’s total orders for the Bhadla-Fatehpur HVDC line to approximately Rs. 1,196 crore including GST, reinforcing the company’s position in the high-voltage direct current (HVDC) transmission segment.

The ±800 kV HVDC line utilizes advanced technology to transmit large power loads over long distances with low losses, connecting renewable energy from Rajasthan to demand centers in Northern India.

Diamond Power is among India's largest manufacturers of conductors with integrated aluminium rod mills and NABL-accredited in-house testing up to 765 kV, supporting its capability to meet the demanding quality standards of this project.

Highlights

  • Orders valued at Rs. 488.18 crore including GST (Rs. 413.71 crore excluding GST) from Adani Energy Solutions Limited.
  • Supply of 6,660 km of AL-59 conductors for the Uttar Pradesh and Madhya Pradesh spans of the ±800 kV HVDC Bhadla-Fatehpur transmission project.
  • Delivery deadline is set for December 31, 2027, with monthly shipments to match project requirements.
  • Total contract value for the Bhadla-Fatehpur HVDC line for Diamond Power is now around Rs. 1,196 crore including GST.
  • Diamond Power’s manufacturing facilities include advanced aluminium rod mills and high voltage testing certified up to 765 kV.
  • The orders are not related party transactions and do not involve promoter group interests.

Key Data Snapshot

Order value including GSTRs. 488.18 crore
Order value excluding GSTRs. 413.71 crore
Total conductor quantity6,659.66 km
AL-59 Lapwing conductor quantity5,692.66 km
AL-59 Zebra conductor quantity967 km
Order awarding entityAdani Energy Solutions Limited
Project project completion deadline31 December 2027
Transmission voltage±800 kV HVDC
Project coverageUttar Pradesh and Madhya Pradesh portions
Total contract value for Bhadla-Fatehpur project (including GST)Rs. 1,196 crore

What happened

  • Diamond Power Infrastructure Limited received two purchase orders from Adani Energy Solutions Limited on November 25, 2026.
  • The orders are for supplying AL-59 Lapwing and Zebra conductors totaling 6,660 km for the ±800 kV HVDC Bhadla-Fatehpur transmission project.
  • The aggregate order value including GST is Rs. 488.18 crore (Rs. 413.71 crore excluding GST).
  • Deliveries will be completed by December 31, 2027, as per project schedule.

Key details

  • The conductors will cover the Uttar Pradesh and Madhya Pradesh portions of the transmission line.
  • The purchase orders require design, engineering, manufacture, testing, packing and supply on delivered-at-place (DAP) basis.
  • The orders add to Diamond Power’s previous Rs. 707.80 crore order for the same project.
  • No promoter or related party interest is involved in this transaction.

Strategic context

  • The ±800 kV HVDC line is the highest voltage HVDC transmission level in India, enabling efficient power transfer with low losses.
  • The Bhadla-Fatehpur link is a key renewable energy corridor connecting Rajasthan’s green power to northern demand centers.
  • Diamond Power is among India’s largest conductor manufacturers with integrated aluminium rod mills and high-voltage testing facilities.
  • This order strengthens Diamond Power's foothold in the specialized HVDC transmission sector.

Management commentary

  • Mr. Kavish Shah, Vice President – Corporate Strategy, highlighted the confidence Adani Energy Solutions places in Diamond Power through repeat orders.
  • He emphasized the company's ability to meet demanding HVDC conductor specifications with integrated production and testing capabilities.
  • He noted Diamond Power’s readiness to participate in additional HVDC and green energy corridor projects across India.

Background and context

  • Diamond Power Infrastructure Limited manufactures LV to EHV power cables, control cables, solar DC and EV charging cables, and conductors.
  • The company serves sectors including power, infrastructure, oil & gas, renewables, real estate, and data centers.
  • The Bhadla-Fatehpur project is a ±800 kV, 6,000 MW corridor spanning approximately 950 km, developed by Adani Energy Solutions.

More News on Order Wins

View all

Latest corporate announcements and market updates in Order Wins.

View all news
Diamond Power Infrastructure Secures Rs. 488.18 Crore…