Deccan Gold Mines Boosts Q2 FY2027 Gold Output to 135 Kilos with Rs. 13.91 Crores Profit; Initiates Kyrgyzstan Gold Dispatch

The company confirms operational profitability at Swarnagiri and Kyrgyzstan’s Altyn-Tor amid Rs. 137 Crores capital raise for exploration projects, including Finland

Deccan Gold Mines Limited disclosed a significant increase in gold production to 135 kilos in Q2 FY2027 from the Swarnagiri project and highlighted initial gold doré dispatch from Kyrgyzstan's Altyn-Tor project. The company reported strong profitability with a PAT of Rs. 13.91 Crores for the quarter and Rs. 20 Crores in H1 FY2027, underscoring successful operational execution across India and overseas projects. Additionally, the firm is raising Rs. 137 Crores to fund further exploration, including critical mineral assets in Finland and gold projects abroad.

Just now|DECNGOLD-6.42%
Deccan Gold Mines Limited512068Earnings Call Transcript

Deccan Gold Mines Limited

Earnings Call Transcript

Deccan Gold Mines Limited reported a rise in gold production to 135 kilos during Q2 FY2027 from its Swarnagiri mine, with a quarterly profit after tax of Rs. 13.91 Crores. The company also commenced gold doré shipment from its recently commissioned Altyn-Tor gold project in Kyrgyzstan and is raising Rs. 137 Crores for expanding exploration initiatives, including in Finland.

Swarnagiri Gold Mine increased its gold production from 89 kilos in Q1 FY2027 to 135 kilos in Q2, averaging approximately 40 kilos per month with expectations to scale up to one ton annually after obtaining new approvals.

Gold recovery rates achieved between 90% to 95% demonstrate the effectiveness of the company's processing techniques at Swarnagiri, contributing to improved profitability.

The company's profit after tax reached Rs. 13.91 Crores in Q2 FY2027, up from around Rs. 6 Crores in the previous quarter, accumulating to Rs. 20 Crores profit in the first half of FY2027, reflecting approximately 50% PAT margin and about 70% EBITDA margin for the gold mining business.

Deccan Gold Mines has dispatched its first 1.2-kilo gold doré consignment from the Altyn-Tor project in Kyrgyzstan to a government-owned refinery, which processes doré and sells refined gold to the national bank, completing the revenue cycle.

The company's Swarnagiri operations include an on-site refinery producing 24 carat gold sold directly to jewelers, differing from the Kyrgyzstan process, but both routes are consistent with industry practices like those at Hutti Gold Mines in India where doré is shipped to external refineries for processing and sale.

Highlights

  • Swarnagiri gold production up to 135 kilos in Q2 FY2027, averaging 40 kilos per month.
  • Gold recovery rate solid at 90-95% at Swarnagiri.
  • Profit after tax increased to Rs. 13.91 Crores in Q2 FY2027 and Rs. 20 Crores in H1 FY2027.
  • First 1.2-kilo gold doré consignment dispatched from Kyrgyzstan Altyn-Tor project.
  • Rs. 137 Crores capital raised to fund exploration, including projects in Finland and critical minerals sector.
  • New approvals expected to enable Swarnagiri to scale production to nearly one ton per annum.

Key Data Snapshot

Gold production in Q2 FY2027 from Swarnagiri135 kilos
Gold production in Q1 FY2027 from Swarnagiri89 kilos
Gold recovery rate90%-95%
Profit after tax in Q2 FY2027Rs. 13.91 Crores
Profit after tax in H1 FY2027Rs. 20 Crores
First gold doré consignment from Kyrgyzstan Altyn-Tor1.2 kilos
Capital raised for exploration fundingRs. 137 Crores
Date of Kyrgyzstan gold project commissioning12 September 2026

What happened

  • Deccan Gold Mines increased gold output to 135 kilos in Q2 FY2027 from Swarnagiri mine, up from 89 kilos in Q1 FY2027.
  • Company achieved 90% to 95% gold recovery in processing operations at Swarnagiri.
  • First gold doré consignment of 1.2 kilos dispatched from Altyn-Tor gold project in Kyrgyzstan.
  • Q2 FY2027 profit after tax rose to Rs. 13.91 Crores, with Rs. 20 Crores accumulated in the first half of the fiscal year.
  • Deccan Gold Mines is collecting Rs. 137 Crores recently approved funding for exploration projects including Finland and critical minerals.

Key details

  • Swarnagiri's gold production is expected to scale up to nearly one ton per annum with new approvals underway.
  • Kyrgyzstan operations send doré to government refinery for processing and sale to the national bank, following mandatory local export processes.
  • Swarnagiri hosts its own refinery, providing refined 24 carat gold bars sold domestically to jewelers.
  • Raised funds will support development of exploration projects in India, Finland, and critical mineral resources.
  • The company's overseas project commissioning in Kyrgyzstan on 12 September 2026 reflects its execution capabilities across jurisdictions.

Strategic context

  • Deccan Gold Mines is focusing on critical minerals expected to impact mining over the next 10 to 20 years.
  • The firm contests with international players to secure a diverse portfolio of assets, positioning itself for future growth potentials.
  • Expanding into overseas jurisdictions while maintaining domestic projects demonstrates the company’s balanced growth strategy.

Regulatory and governance context

  • The company awaits finalization of product refining and revenue receipt processes in Kyrgyzstan following shipment of doré bars.
  • Capital raising approvals by BSE were delayed but now completed, enabling fund collection and project financing.