Order covers complete execution of two +300/-200 MVAR synchronous condensers for RE integration in 35 months
Bharat Heavy Electricals Limited (BHEL) has received a domestic order from Power Grid Corporation of India Limited for the design, engineering, manufacturing, supply, erection, testing, and commissioning of two +300/-200 MVAR Synchronous Condensers at Kalyanpur, Gujarat. The project, supporting renewable energy integration, is valued between Rs. 600 crore and Rs. 900 crore excluding GST with a 35-month execution timeline.
Bharat Heavy Electricals Limited
Order Wins
Bharat Heavy Electricals Limited (BHEL) has been awarded a significant domestic contract by Power Grid Corporation of India Limited for the establishment of two +300/-200 MVAR synchronous condensers at Kalyanpur, Gujarat. The project supports integration of renewable energy projects and is valued between Rs. 600 crore and Rs. 900 crore excluding GST.
The scope of work includes design, engineering, manufacturing, supply, erection, testing, and commissioning of the synchronous condensers, which form part of the transmission system to support renewable energy projects in the Jam Khambhaliya Renewable Energy Zone in Gujarat.
The order is to be executed over a period of 35 months from the date of award, indicating a medium-term project timeline for BHEL.
The order was awarded by Power Grid Corporation of India Limited, a Government of India enterprise, on behalf of its Project Special Purpose Vehicle (SPV) Company.
BHEL has confirmed that neither promoters nor related party transactions are involved in relation to this contract.
Highlights
- Order received from Power Grid Corporation of India Limited for two synchronous condensers at Kalyanpur, Gujarat.
- Capacity of each condenser: +300/-200 MVAR.
- Project value range: Rs. 600 crore to Rs. 900 crore, excluding GST.
- Project involves complete end-to-end solutions: design through commissioning.
- Execution timeline fixed at 35 months.
- Order supports power integration from renewable energy projects in Jam Khambhaliya Renewable Energy Zone (REZ).
Key Data Snapshot
What happened
- BHEL received an order from Power Grid Corporation of India Limited for two synchronous condensers at Kalyanpur, Gujarat.
- The order entails complete project delivery including design and commissioning.
- This contract is linked with the transmission system to facilitate renewable energy integration in the Jam Khambhaliya zone.
Key details
- Each synchronous condenser capacity is +300/-200 MVAR.
- The project value is estimated between Rs. 600 crore to Rs. 900 crore excluding GST.
- The execution period of the project is 35 months.
- The order is awarded domestically by a Government of India undertaking on behalf of its SPV Company.
Transaction details
- No promoter or related party interest is involved in this contract.
- The transaction is not classified as a related party transaction.
- BHEL will execute all phases from manufacturing to commissioning.
Background and context
- Synchronous condensers support transmission systems by stabilizing voltage and aiding integration of renewable energy.
- The project supports Power Grid’s infrastructure development in Gujarat’s Jam Khambhaliya RE Zone.
Highlights
- Order received from Power Grid Corporation of India Limited for two synchronous condensers at Kalyanpur, Gujarat.
- Capacity of each condenser: +300/-200 MVAR.
- Project value range: Rs. 600 crore to Rs. 900 crore, excluding GST.
- Project involves complete end-to-end solutions: design through commissioning.
- Execution timeline fixed at 35 months.
- Order supports power integration from renewable energy projects in Jam Khambhaliya Renewable Energy Zone (REZ).
Disclosures
- SEBI Listing Obligations and Disclosure Requirements Regulations, 2015 - Regulation 30
No related party transaction
No promoter interest in the counterparty
More News on Order Wins
View allLatest corporate announcements and market updates in Order Wins.
Midwest Energy Wins Rs. 7,280 Crore LOI from Indian Government for Rare Earth Magnet Manufacturing Project
Midwest Energy Limited has been awarded a Letter of Intent by the Ministry of Heavy Industries, Government of India, as the successful bidder under a Rs. 7,280 crore scheme aimed at promoting domestic manufacturing of sintered rare earth permanent magnets with a project capacity of 1,200 metric tonnes per annum.
Read Full StoryAshoka Buildcon Subsidiary's SAR 351.37 Crore Saudi Arabia Hotel Construction Project Cancelled by Employer
Ashoka Buildcon Limited announced that its wholly owned Saudi Arabian subsidiary, in joint venture with BEC Arabia Contracting Co., has had its SAR 351,372,308.67 (Rs.846.38 Crore) contract for the Diriyah II One Hotel project cancelled by the Employer, Diriyah Company, due to internal reasons.
Read Full StoryDiamond Power Infrastructure Wins Rs. 707.80 Crore Order to Supply AL-59 Conductors for ±800 kV HVDC Bhadla-Fatehpur Project
Diamond Power Infrastructure Limited has secured a purchase order valued at Rs. 707.80 crore including GST from Adani Energy Solutions Limited for the supply of 9,059.33 km of AL-59 conductors for the ±800 kV HVDC Bhadla-Fatehpur transmission project. This contract marks the company's entry into the high-voltage direct current (HVDC) transmission segment in India.
Read Full Story