WhatsApp
backNews Article

Adani Energy Solutions Wins Rs 500 Crore Bihar Transmission Project to Evacuate 2400 MW from Pirpainti Power Plant

Project adds 881 ckm of transmission lines and 3,160 MVA capacity, expected to complete by Q4 2028 via SPV Vikramshila Power Transmission Ltd

Adani Energy Solutions Limited has won a Rs 500 crore transmission project in Bihar to evacuate 2400 MW of power from the upcoming Pirpainti Ultra Super Critical Thermal Power Plant. The project will add 881 circuit kilometres of transmission lines and 3,160 MVA transformation capacity, strengthening Bihar's transmission network and enhancing supply reliability with completion expected by the last quarter of 2028.

Just now|ADANIENSOL-1.11%
Adani Energy Solutions LtdADANIENSOLOrder Wins

Adani Energy Solutions Ltd

Order Wins

Adani Energy Solutions Limited has secured a transmission project worth approximately Rs 500 crore to evacuate 2,400 MW of power from the upcoming Pirpainti Ultra Super Critical Thermal Power Plant in Bihar, strengthening the state's power transmission network.

The project, titled “Evacuation of Power from 3X800 MW STPP Pirpainti,” will be executed through the Special Purpose Vehicle Vikramshila Power Transmission Ltd and is slated for delivery by the last quarter of 2028.

This infrastructure addition will enhance Bihar’s transmission backbone by providing greater grid reliability and resilience while supporting growing power demand.

On completion, the project will add 881 circuit kilometres (ckm) of transmission lines and 3,160 MVA of transformation capacity to AESL's portfolio, increasing their total network to 30,683 ckm and 146,585 MVA respectively.

The scope includes constructing four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli, and Begusarai, alongside multiple 400 kV and 220 kV lines connecting key locations such as Pirpainti, Jhanjharpur, Begusarai, and Bakhtiyarpur.

The project will also involve looping in and looping out (LILO) existing transmission lines and constructing 400 kV line bays to support network capacity and stability.

Highlights

  • Project secures an annual tariff of approximately Rs 500 crore upon commissioning.
  • Adds 881 ckm of transmission lines and 3,160 MVA transformation capacity.
  • Part of AESL's transmission portfolio now totaling 30,683 ckm and 146,585 MVA.
  • Completion expected by Q4 2028 via SPV Vikramshila Power Transmission Ltd.
  • Includes construction of four GIS substations and multiple high-voltage transmission lines.
  • Enhances transmission network reliability and evacuation capacity for Bihar's power demand.

Key Data Snapshot

Project TitleEvacuation of Power from 3X800 MW STPP Pirpainti
Power Evacuation Capacity2400 MW
Project TariffRs ~500 crore annual tariff
Transmission Lines Addition881 circuit kilometres
Transformation Capacity Addition3,160 MVA
Project Delivery TimelineLast quarter of 2028
Special Purpose VehicleVikramshila Power Transmission Ltd
Company Transmission Portfolio Post-Project30,683 ckm lines and 146,585 MVA capacity
Project Capex~Rs 91,500 crore (AESL transmission capex)

What happened

  • Adani Energy Solutions Limited won a competitive bidding transmission project in Bihar for evacuating power from the upcoming 2400 MW Pirpainti Ultra Super Critical Thermal Power Plant.
  • The project will be implemented by a special purpose vehicle named Vikramshila Power Transmission Ltd.
  • It aims to strengthen Bihar’s transmission network and improve grid reliability by adding significant transmission infrastructure.

Key details

  • Project provides an annual tariff of approximately Rs 500 crore post-commissioning.
  • This project adds 881 circuit kilometres of transmission lines and 3,160 MVA transformation capacity to AESL’s portfolio.
  • Infrastructure includes four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli, and Begusarai.
  • Transmission lines span 400 kV DCDS and 220 kV DCDS connections among Pirpainti, Jhanjharpur, Begusarai, Bakhtiyarpur and Bethauli.
  • Includes looping in and out (LILO) of existing transmission lines and construction of 400 kV line bays at Bakhtiyarpur GSS.

Strategic context

  • This project is part of AESL's expanding transmission portfolio, increasing their cumulative network and transformation capacity to 30,683 ckm and 146,585 MVA respectively.
  • AESL's total transmission capital expenditure stands at around Rs 91,500 crore following this project addition.
  • The transmission infrastructure will facilitate effective evacuation of power from the Pirpainti power plant supporting Bihar’s energy security and demand growth.

Background and context

  • Adani Energy Solutions Limited is a leading private sector power transmission and distribution company in India.
  • AESL operates a large transmission network and serves approximately 13 million consumers in retail electricity distribution.
  • The company is expanding into smart metering and integrated energy solutions with a focus on reliability and sustainability.

More News on Order Wins

View all

Latest corporate announcements and market updates in Order Wins.

View all news
Adani Energy Solutions Wins Rs 500 Crore Bihar | Stockk News