ACME Solar Holdings Commissions 35.81 MW Battery Energy Storage System at Tata FDRE Power Project

Operational capacity of 35.81 MW / 148.645 MWh commissioned on November 20, 2026; commercial operation date set for November 22, 2026 under PPA with Tata Power Company Limited

ACME Solar Holdings Limited, via its subsidiary ACME Sigma Urja Private Limited, has commissioned 35.81 MW / 148.645 MWh of the Battery Energy Storage System out of the 50 MW / 209 MWh capacity at the Tata FDRE Power Project in Rajasthan. The commercial operation date is set for November 22, 2026, with a power purchase agreement signed with Tata Power Company Limited.

8 hours ago|ACMESOLAR+0.00%
ACME Solar Holdings Limited544283ACMESOLARCapacity Expansion

ACME Solar Holdings Limited

Capacity Expansion

ACME Solar Holdings Limited, through its wholly-owned subsidiary ACME Sigma Urja Private Limited, has commissioned 35.81 MW of the Battery Energy Storage System at the Tata FDRE Power Project in Rajasthan as of November 20, 2026.

The commissioned Battery Energy Storage System (BESS) has a discharge capacity of 35.81 MW and energy capacity of 148.645 MWh, out of the total 50 MW / 209 MWh (installed capacity 50 MW / 220 MWh) planned for the project.

The Tata FDRE Power Project is located at Village Neemri, Tehsil Rawatbhata, District Chittorgarh in Rajasthan.

Currently, only the BESS component of the project has been commissioned, with its Commercial Operation Date (COD) scheduled for November 22, 2026.

The power generated and stored under this project will be supplied pursuant to a Power Purchase Agreement (PPA) signed with Tata Power Company Limited.

Highlights

  • Battery Energy Storage System capacity commissioned: 35.81 MW / 148.645 MWh
  • Total BESS capacity planned: 50 MW / 209 MWh (installed capacity: 50 MW / 220 MWh)
  • Project location: Neemri village, Rawatbhata, Chittorgarh, Rajasthan
  • Commercial Operation Date for BESS: November 22, 2026
  • Project covered under PPA with Tata Power Company Limited

Key Data Snapshot

BESS Commissioned Discharge Capacity35.81 MW / 148.645 MWh
Total BESS Capacity Planned50 MW / 209 MWh (Installed capacity: 50 MW / 220 MWh)
Commercial Operation DateNovember 22, 2026
Project LocationVillage Neemri, Tehsil Rawatbhata, District Chittorgarh, Rajasthan
Power Purchase Agreement CounterpartyTata Power Company Limited

What happened

  • ACME Solar Holdings Limited has commissioned the Battery Energy Storage System (BESS) portion of the Tata FDRE Power Project.
  • The commissioned discharge capacity is 35.81 MW with an energy storage of 148.645 MWh out of the planned 50 MW / 209 MWh capacity.
  • The commissioning occurred on November 20, 2026.

Key details

  • Only the BESS component has been commissioned so far; full project commissioning is pending.
  • The Commercial Operation Date for the BESS component is scheduled for November 22, 2026.
  • The project has a signed Power Purchase Agreement with Tata Power Company Limited.
  • The project site is located at Village Neemri, Tehsil Rawatbhata, District Chittorgarh, Rajasthan.